Stagger Kiln 1 co-start with Mill 2 by 10 minutes

Back to queue
Load managementhighInfoneeds review· 2026-07-21

Kiln 1 and Raw Mill 2 co-started into the 1011 TOD peak window, pushing rolling MD to 4,680 kVA — only 6.4% headroom below CMD 5,000 kVA. Staggering the second large load by 10 minutes avoids MD coincidence charges.

Potential savings

₹84,000

per month

₹10,08,000 / yr modeled

Root-cause analysis

  • No interlock between Kiln 1 warm-up sequence and Mill 2 start permission.
  • Shift handoff defaults allow simultaneous large-load starts.
  • Peak TOD window (1011) overlaps with routine pyro + grinding ramp.

Recommended action

  1. Immediate: hold Mill 2 start until Kiln 1 load settles below 95% (no CAPEX).
  2. Operator playbook: rotate co-starts so only one large load enters the 1011 TOD window.
  3. Long-term: sequencer interlock + 2 m³ buffer on shared air/process header if dips persist.

MD coincidence window

2026-07-21 09:40 IST

MD coincidence window
AssetLoad %MD contribution (kVA)Comment
Kiln 1108%1,860Above design — critical
Raw Mill 272%640Co-start with Kiln 1
Main incomer94%4,680Rolling 15-min MD peak
What this shows

Two large loads entered the peak TOD band simultaneously. A 10-minute stagger on Mill 2 start keeps rolling MD below the penalty threshold.

Sanity check

Hold Mill 2 start until Kiln 1 load settles below 95%. Monitor rolling MD for 15 min — should drop ≥120 kVA if stagger holds.

Cost–benefit & ROI

MD coincidence risk — potential penalty exposure on CMD breach + peak TOD energy premium.

Tariff scenarios
ScenarioModeled impact / mo
Status quo (co-start)₹84k penalty risk
10-min stagger (no CAPEX)₹0 – ₹12k residual
Sequencer interlock (long-term)₹0 – ₹5k residual

Immediate fix is sequence change only. Long-term: sequencer interlock + buffer (~₹2L) if pressure/throughput dips persist.

  • 6.4%8%+ MD headroom
  • Reduced peak TOD kWh share
  • Lower transformer stress

Risks & mitigations

Risks and mitigations
RiskMitigation
Pressure/throughput dip on step-loadAdd +2 min stagger before relaxing hold; monitor kiln draft.
Operator re-enables both earlyLog override; require supervisor PIN to override.

KPIs & alerts

KPI targets and alerts
KPITargetAlert
Co-starts in 10–11 TOD0 / shift>0
Rolling MD headroom≥ 8%< 6%
Kiln 1 load at Mill 2 start< 95%≥ 95%

Commissioning & verification

  1. Confirm stagger rule in shift log for 3 consecutive shifts.
  2. Capture rolling MD before/after for savings verification (Option C baseline).
  3. Acceptance: zero co-starts in peak TOD for 7 days; MD headroom ≥ 8%.

Ledger entry

Savings verification
IPMVP Option C
Baseline
kiln 1 7d
Period
1 Jul → 31 Jul 2026
Potential
₹84,000
Realised
₹0
Status
Pending

Manager takeaway

A 10-minute sequence change avoids ₹84k/mo MD risk with zero CAPEX. Long-term interlock locks in the discipline.