Prescription · Full case

Sequence three 75 kW VFD compressors — stop part-load pile-up

Back to queue
Compressed airhighInfoneeds review· 2025-08-30

Three 75 kW VFD compressors were observed modulating simultaneously when a two-unit strategy would have met demand, adding ~130 MWh/year of avoidable energy.

Potential savings

₹1,08,000

per month

₹12,96,000 / yr modeled

Root-cause analysis

  • No central sequencereach compressor obeys its own pressure switch.
  • Overlapping set-points keep all units cutting in.
  • Operator habit leaves all three enabled to "avoid dips," sacrificing efficiency.

Recommended action

  1. Immediate set-point reset (no CAPEX): raise unload band and extend timer so only lead+lag stay online.
  2. Operator playbook: rotate lead weekly; never leave all three enabled 'to avoid dips'.
  3. Long-term: sequencer PLC + receiver buffer (~₹68.5L) for sub-1-year payback.

Event snapshot (evidence)

2024-06-01 06:30 IST

Event snapshot (evidence)
UnitPower (kW)% of 75 kWComment
Unit-14357%Part-load
Unit-25472%Part-load
Unit-36891%Near loaded
Combined165Three online at partial load
What this shows

Three machines stayed online while demand fit a sequenced two-unit strategy. The third unit idling/modulating adds approximately 130 MWh/year.

Sanity check

During a similar load window, shut the lowest-loaded unit under supervision. Stable pressure proves two units suffice when sequenced correctly. Log header pressure, kW, and alarms for 1530 minutes to confirm.

Cost–benefit & ROI

130,000 kWh/yr from the third unit idling/modulating.

Tariff scenarios
Tariff (₹/kWh)Annual saving
7.00₹9.1L
8.00₹10.4L
10.00₹13.0L

Capex for sequencer + sensors: ₹6L₹8.5L ⇒ ~9-month payback at ₹8/kWh. Side gains include trimmed peak kW, fewer lag run-hours, quieter operation, and more headroom.

  • Trimmed peak kW on shared incomer
  • Fewer lag run-hours → extended bearing life
  • Quieter plant floor during off-peak
  • 75 kW of peak capacity freed for process loads

Risks & mitigations

Risks and mitigations
RiskMitigation
Pressure dip on step-loadsAdd +2 m³ receiver and keep Lag-1 armed with 30 s delay.
Operator overrideSOP at panel, weekly audit of set-points, alarm if all three online >10 min.
Sensor driftQuarterly calibration with dual-sensor plausibility check (±0.1 bar).

KPIs & alerts

KPI targets and alerts
KPITargetAlert
Minutes with 3 units ON≤ 5%>5% in any 24 h
Time outside 6.5–7.3 bar≤ 5%>5%
Starts per shift per unit≤ 10>10
Unloaded time per unit≤ 10% of run time>10%

Commissioning & verification

  1. Calibrate header sensor and confirm 6.57.3 bar band.
  2. Run two-unit trial (Lag-2 disabled) to prove stability under new rules.
  3. Acceptance (24 h):5% minutes outside band, ≤10 starts/shift, ≤10% unload time, ≥95% minutes with ≤2 units.
  4. Lock in set-points, store PLC recipe, and pin SOP at panel.

Manager takeaway

Two 75 kW units can carry the load. Sequencing discipline now plus a PLC and small receiver recovers roughly ₹10L₹12L per year with <1-year payback and boosts reliability.