Leak survey — instrument air loop B

Back to queue
Compressed airlowInfoverifyingPending· 2026-07-19

Ultrasonic hotspots mapped on night round

Potential savings

₹15,000

per month

₹1,80,000 / yr modeled

Root-cause analysis

  • Ultrasonic hotspots mapped on night round

Recommended action

  1. Close tagged fittings; re-scan loop B after 48 h.

Anomaly window

2026-07-21 09:30:00 IST

Anomaly window
AssetLoad %Comment
kiln 1108%Above design
mill 172%Normal
comp 254%Normal
What this shows

Demand 14% above design during 1011 TOD peak; MD coincidence risk.

Sanity check

Confirm finding against live load for the named assets. Log header pressure, kW, and alarms for 1530 minutes to validate.

Cost–benefit & ROI

Modeled addressable: ₹15,000/mo based on MD coincidence · peak TOD window.

Repair fittings · low CAPEX

KPIs & alerts

KPI targets and alerts
KPITargetAlert
Rule confidence≥ 72%< 62%
Action by due dateVerifyingOverdue

Commissioning & verification

  1. Close tagged fittings; re-scan loop B after 48 h.

Ledger entry

Savings verification
IPMVP Option A
Baseline
air loop b
Period
15 Jun → 15 Jul 2026
Potential
₹15,000
Realised
₹12,800
Status
Confirmed by operations

Manager takeaway